Complete kits for six hall infills, including structural engineering, fasteners, the DoP and certification records.
Starting point
The order had an exceptionally short programme: the published record states that only one week separated contract signature from completion of the kits.
Solution and delivery
OCELIS prepared the system solution with Saint-Gobain, manufactured the complete kits and supplied the structural engineering, all fasteners, the Declaration of Performance and certification records.
Outcome or current status
All six kits were completed within the stated one-week period. Assembly was already under way when the source was published; this page therefore does not claim completion of the entire build.
The facts come from a public post by OCELIS founder Robin Vašnovský. It does not identify the client or project location, so neither is inferred here; only the substantiated delivery scope and status are published. Open the public source ↗